4.2 Work Done by a Variable Force
In many cases, the force does not remain constant during the process of doing work. For example, as a rocket moves away from the Earth, work is done against the force of gravity, which varies as the inverse square of the distance from the Earth's centre. Similarly, the force exerted by a spring increases with the amount of stretch. How can we calculate the work done in such situations?
Figure 4.5 shows the path of a particle in the - plane as it moves from point to point . The path has been divided into short intervals of displacements , , , and , , , , are the forces acting during these intervals, respectively.
During each small interval, the force is supposed to be approximately constant. So, the work done for the first interval can then be written as:
and in the second interval:
and so on. The total work done in moving the object can be calculated by adding all these terms.
or
We can examine this graphically by plotting versus as shown in Fig. 4.6. The displacement has been sub-divided into the same equal intervals. The value of at the beginning of each interval is indicated in the figure.
Now the th shaded rectangle has an area which is the work done during the th interval. Thus, the work done given by Eq. 4.4 equals the sum of the areas of all the rectangles. If we sub-divide the distance into a large number of intervals so that each becomes very small, the work done given by Eq. 4.4 becomes more accurate. If we let each to approach zero, then we obtain an exact result for the work done, such as:
If this limit approaches zero, the total area of all the rectangles (Fig. 4.6) approaches the area between the verses curve and -axis from to as shown shaded in Fig. 4.7.
Thus, the work done by a variable force in moving a particle between two points is equal to the area under the verses curve between the two points and as shown in Fig. 4.7.
Example 4.1
A force acting on an object varies with distance as shown in Fig. 4.8. Calculate the work done by the force as the object moves from to .
Solution
The work done by the force is equal to the total area under the curve from to . This area is equal to the area of the rectangular section from to , plus the area of triangular section from to .
Hence
Work done represented by the area of rectangle
Work done represented by the area of triangle
Therefore, the total work done =