150 workers were engaged to finish a piece of work in a certain number of days. Five workers dropped the second day, five more workers dropped the third day and so on. It takes 10 more days to finish the work now. Find the number of days in which the work was completed.

Let the work originally be finished in ( n ) days by 150 workers, so total work = ( 150n ) man-days.

Now workers: 150 on day 1, 145 on day 2, 140 on day 3, … (A.P. with ( a=150 ), ( d=-5 )).

It takes ( n+10 ) days. Number of workers on the last day: [ a_{n+10} = 150 + (n+9)(-5) = 150 - 5n - 45 = 105 - 5n. ]

Sum of workers over ( n+10 ) days: [ S = \frac{n+10}{2}\bigl[2\cdot 150 + (n+9)(-5)\bigr] = \frac{n+10}{2}\bigl(300 - 5n - 45\bigr) = \frac{n+10}{2}(255 - 5n) = \frac{5(n+10)(51 - n)}{2}. ]

This equals the original work: [ \frac{5(n+10)(51-n)}{2} = 150n \implies (n+10)(51-n) = 60n ] [ 51n - n^2 + 510 - 10n = 60n \implies -n^2 + 41n + 510 = 60n ] [ -n^2 -19n + 510 = 0 \implies n^2 + 19n - 510 = 0. ]

[ n = \frac{-19 \pm \sqrt{361 + 2040}}{2} = \frac{-19 \pm \sqrt{2401}}{2} = \frac{-19 \pm 49}{2}. ] Positive root: ( n = 15 ).

Total days taken now = ( 15+10 = 25 ).

Answer: 25 days